NXGN ERP — Project Dashboard

NXGN ERP — Milestone Projection & Velocity Analysis
June 18, 2026
Last refreshed:
UAT Readiness
Badges show development status only (dev-complete = zero open stories); UAT window dates are under re-evaluation and intentionally not shown.

Value Chains & the September 1 Question

Epics were reorganized (Jun 6) from functional modules into six value chains — each chain epic is its UAT wave: one epic = one complete business cycle = one end-to-end UAT pass. The module view lives on as mod-* labels; cross-chain stories sit in the first chain whose vertical slice needs them.

  • September 1 holds. Scope trued to pts by the Jun 4–10 chain audits. Migration ( pts) is a JV-owned workstream off the scrum team — a parallel lane to the Sep-1 cutover, not sprint capacity — leaving functional scope pts, of which Business Intelligence ( pts) is a post-go-live wave.
  • The go-live-critical set is A–D = pts. At the adopted pts/sprint basis, S9–S12 capacity is pts (net–gross) → A–D lands by Sep 1 with a ~ pt fast-follow band trailing into September.
  • Per-story banding is adopted at S9 planning Jun 16 (s9-rebaseline-banding.md). The binding constraint is migration source files, not points.
Text size:
🚀
Target Go-Live Date
September 1, 2026
Full go-live incl. all UAT complete  ·  days from today
%
Features Built ( / pts — as of )
Sprint 9 · ACTIVE
Jun 16 – Jun 30, 2026 · S8 closed 97/97
pts planned · DoR-gated, not yet in Jira
pts/sprint
Planning basis (S9–S12) · -pt capacity
days
Schedule Buffer (back-to-back sprints)
Bottom Line for Leadership
1 Are we on track?
● YES — on track for September 1

The team is completing work faster than the launch plan requires and just posted its best two-week output on record. Everything that must be live for go-live fits the cycles that remain, with development finishing about three weeks before the date — a -day buffer. That spare time absorbs surprises; it doesn't push the date.

2 What are the biggest risks?
● ONE the team can't fix alone

The one risk effort can't solve is data migration: a few legacy source files — old buyer balances and purchase & stock records — are still outstanding and need the Steering Committee to release them by June 16. Everything else is in hand: keeping sprints back-to-back, lining up business testers per wave, and absorbing newly-found requirements into spare capacity rather than the date.

3 Do we have the people, time & budget?
● YES — with margin to spare

People: 3 developers + 2 QA, delivering pts/sprint against the pts of go-live-critical work left — capacity runs ahead of need. Time: development completes , then a 21-day cutover window. Budget: tracking ~26% under the approved ₱12.4M. The binding constraint isn't money, people, or time — it's the migration files.

Ask About This Project
Ask anything about delivery, scope, risks, budget, or the September 1 timeline. Answers are generated from the project's live data (refreshed nightly).
Sprint Planner
Sprint 9 (Jun 16–30) · live Jira . Ask about the backlog or give a planning directive — the plan re-orders from the live backlog (real stories only). Display-only — never written to Jira.
◆ AI Planning Analysis
Loading analysis…
Velocity target pts · stories that fit are the commitment; the rest fall below the line. Re-prompt to re-prioritize.
CURRENT SPRINT — IN PROGRESS
Sprint 9 — Jun 16–30, 2026
Planning basis pts. S8 closed 97/97 (100%, 0 carryover). A re-certification + B UAT both open Jun 17. The S9 commitment is DoR-gated and not yet assigned in Jira — build it live on the Sprint Planner sub-view.
Planning basis (pts/sprint)
Sep-1-critical open (A–D)
Days to go-live
S9 is sequenced to the imminent UAT windows (A re-cert + B UAT) plus the Treasury / multi-entity foundation that clears the Wave-C gate. Open the Sprint Planner to ask the planner to re-prioritize live — e.g. "prioritize P2P but hold a 120-pt velocity."
NEXT SPRINT — NOT YET PLANNED
Sprint 10 — Jun 30 – Jul 14, 2026
Planned at S9 close (Jun 30). S10 is timed to the Wave-C UAT window (~Jul 15): it absorbs the deferred Treasury / financial-close set — consolidation, group statements, intercompany stock transfer, the P2P close spine and treasury ops — plus the prerequisites JV's ~July migration load depends on.
Forward look only. Use the Sprint Planner to sketch S10 — e.g. "plan the next sprint focused on Treasury & financial close at 115 pts."
ACTIVE SPRINT — COMMITTED JUN 2
Sprint 8 — Jun 2 – Jun 16, 2026
S8 delivered 97/97 (100%, 0 carryover) · 20 stories. It closed Wave B — Fixed Assets (NXGN-260/261/263 + 1681 = 20) and Materials enhancements (1678/1679/1680 = 9) for Wave B; ships the COFP cluster (NXGN-1668 issuance 5 + 1385 turnover 5 + 1386 override-removal 3 = 13) plus Sales/CRM enhancements (1215/1216 = 10); and seeds Wave C with Trial Balance + SoD control (NXGN-431/1684 = 11) and the Bank reconciliation engine (NXGN-254 = 5). Cross-cutting: clickable entity links (NXGN-1686, 8), approval-threshold + dev-DB reset (1687/1688, 8). Migration starts on the new dual-source model: load the Q1 test slice (NXGN-1689, 8) + item master (NXGN-1690, 5). Carried to S9: the T2C entity/IC + first-close set (Wave C gate), banding adoption (Jun 16), and the BI data layer.
S8 committed scope
97 pts
20 stories · FA+Materials+COFP+W4 seed+migration start
Next focus → Wave C
Treasury & Close
S8 Committed Jun 2 — 97 pts / 20 stories (S7 closed 124/124 · 100%)
Wave B epics DONE
AP, Procurement & Materials epics complete; FA registry/depreciation/revaluation done in S7. 0 carryover.
Wave B — core build done at S7
34 pts dev backlog (FA 260/261/263 + 1681 = 23; Materials 1678/1679/1680 = 11) to close in S8. UAT opens on the dev-complete core.
Scope (live Jira Jun 17)
707 pts remaining (post-S8-close; Jun-17 grooming net +9). Migration (123) is JV-owned/off-velocity and BI (77) post-go-live → Sep-1-critical = A–D = 507 pts vs 460 (S9–S12 @115) — A–D Band-1 (206) fits; full A–D lands with a ~47–93 pt Band-2 fast-follow band. Per-story banding is the S9 baseline; see s9-rebaseline-banding.md.
Sprint 8 — Committed
S8 COMMITTED · JUN 2 – JUN 16, 2026
97
pts committed
WB close 29 + COFP/Sales 23 + WC seed 16 + enablers 16 + migration 13
20 stories · within ~101 recent pace
WAVE B CLOSE
29 pts
⚡ Must-Do · Wave B close
FA 260/261/263+1681 (20) closes NXGN-205
Materials 1678/1679/1680 (9)
MIGRATION START + ENABLERS
29 pts
Dual-source migration begins
Migration Q1 slice + item master (1689/1690 = 13)
Clickable links 1686 (8) · approval/dev-DB 1687/1688 (8)
WAVE C SEED (175 pts open)
16 in S8
Critical-path chain · TIGHT
Trial Balance 431 + SoD 1684 (11) + Bank recon 254 (5);
Band-1 set (109 beyond S8: entity/IC + first-close) → S9/S10
S8 delivered 97/97 (100%, 0 carryover) · 20 stories: Wave B close (Fixed Assets 260/261/263 + 1681 = 20, Materials 1678/1679/1680 = 9 — for Wave B), the COFP cluster (NXGN-1668 issuance 5 + 1385 turnover 5 + 1386 override-removal 3 = 13) plus Sales/CRM 1215/1216 (10), Wave C seed (Trial Balance + SoD 431/1684 = 11, Bank recon 254 = 5), cross-cutting enablers (clickable links 1686 = 8, approval/dev-DB 1687/1688 = 8), and the migration start on the new dual-source model (Q1 slice + item master 1689/1690 = 13). NXGN-1384 fee-inclusion was archived Jun 4 (handled at migration, NXGN-1758). Carried to S9: the T2C entity/IC + first-close set (Wave C gate), banding adoption (Jun 16), and the 241/438/256 splits — all already groomed Jun 4–6.
Sprint 8 Story Plan — By Epic
WAVE 3 CLOSE — FIXED ASSETS NXGN-205 ⚡ 20 pts · 4 stories (260/261/263 + 1681) · closes NXGN-205 in S8 (registry/depreciation/revaluation already Done)
Story Key Summary Pts Why in S8
FIXED ASSET MANAGEMENT — NXGN-205 · Wave B · remaining 20 pts (260/261/263 + 1681) · registry/depreciation/revaluation Done in S7 · epic closes in S8
NXGN-260 Asset Transfer and Custodian Tracking 5 Carry from S7 — needed to complete the FA lifecycle and close the Wave B build.
NXGN-261 Asset Disposal and Retirement 5 Carry from S7 — disposal workflows trigger final depreciation and GL postings.
NXGN-263 Fixed Asset Reporting and Audit Trail 5 Carry from S7 — reporting completes UAT sign-off requirements for Wave B.
WAVE 1 FOLLOW-UP — COFP · NXGN-207 5 pts · 1 story (issuance) · NXGN-1385/1386 turnover+override sit in Wave A below · ⚠ Wave A UAT closed — needs a re-test slot
Story Key Summary Pts Why in S8
COLLECTIONS — NXGN-207 · Wave A · 5 pts · COFP issuance; Wave A stories NXGN-1385/1386 depend on it (NXGN-1384 fee-inclusion archived Jun 4 → migration)
NXGN-1668 Collections Officer — Issue Certificate of Full Payment (COFP) on Final Payment Posting 5 Foundational COFP issuance event; DOAS turnover (NXGN-439) + NXGN-1385/1386 all depend on it. Committed in S8.
NXGN-439 ⟳ DOAS re-trigger — re-point the Done DOAS workflow off the manual Fully-Paid flag onto COFP issuance TBD ⚠ ACTION — no Jira story yet. Needed for COFP→DOAS end-to-end (NXGN-439 currently triggers off the manual flag NXGN-1386 removes). Create the story at the Jun 2 review.
WAVE 2 FOLLOW-UP — SALES/CRM · NXGN-119 23 pts · 5 stories · ⚠ Wave A UAT closed Jun 2 — 4 committed in S8 (1215/1216/1385/1386); NXGN-1385/1386 complete the COFP feature
Story Key Summary Pts Why in S8
SALES INVENTORY & CRM — NXGN-119 · Wave A · 23 pts · UAT closed Jun 2 — follow-ups need a re-test slot
NXGN-1385 PDO — Auto-Trigger Unit Turnover Workflow on COFP Issuance 5 COFP feature — depends on NXGN-1668 issuance; schedule together.
NXGN-1386 Documentation Officer — Remove Manual Fully Paid Override from DOAS (Enforce COFP-Driven Status) 2 COFP feature — depends on NXGN-1668; removes the manual flag NXGN-439 currently uses.
NXGN-1215 Sales Manager — Auto-Recalculate Agent Commission on Payment Restructuring 8 Wave A enhancement (UAT-closed follow-up) — depends on NXGN-440; confirm in-wave.
NXGN-1216 Documentation Officer — Capture Individual Unit Title in Inventory (TCT/CCT) 5 Wave A enhancement — unit title capture feeding DOAS.
NXGN-1382 System Admin — Align Module Terminology with PRC and Key User Groups 5 Wave A enhancement — terminology alignment for UAT user groups.
BI INFRASTRUCTURE — NXGN-537 16 pts · 4 stories · foundation (incl. design tokens NXGN-1671) · unblocks dashboards in S9
Story Key Summary Pts Why in S8
BUSINESS INTELLIGENCE & REPORTING — NXGN-537 · Wave E · foundation layer (16 pts of 72 total)
NXGN-1003 System — BI Reporting Data Layer (Materialized Views & Reporting Schema) 5 Foundation layer — all BI dashboards depend on this. Must land before any dashboard stories in S9.
NXGN-1004 System — BI Dashboard Shell & Shared Slicer/Filter Engine 5 Shared navigation/filter component used by all 15+ dashboards — must precede individual dashboard stories.
NXGN-1005 System — BI Data Refresh Architecture & Access Control Matrix 3 Defines refresh schedule and role-based access — required before UAT testers access BI dashboards.
NXGN-1671 System — BI Design Tokens & Responsive Breakpoint Definitions 3 NEW (created Jun 1) — owns brand palette, design tokens & breakpoints (orphaned from NXGN-586); NXGN-587 + all dashboards depend on it.
WAVE 4 START — BANK/TREASURY + GL/BIR + MULTI-ENTITY 175 pts open · 33 stories · chain NXGN-202 (mods: GL/Reporting · Bank/Treasury · Multi-Entity) · window TBD (multi-entity confirmed in MVP — entity/IC + first-close set must land in S9)
Story Key Summary Epic Pts UAT Relevance
BANK MANAGEMENT, RECONCILIATION & TREASURY — NXGN-209 · Wave C · 21 pts (all 3 stories)
NXGN-447 Cashier — Petty Cash Fund Management & Employee Cash Advance Bank/Treasury · W4 8 Cash advance lifecycle — high daily transaction volume in UAT
NXGN-255 Short-Term Cash Flow Projection (13-Week Rolling Forecast) Bank/Treasury · W4 8 Treasury dashboard — leadership-facing; critical for Wave C UAT sign-off
NXGN-254 Automated Reconciliation Matching Engine Bank/Treasury · W4 5 Core reconciliation logic — blocks all bank statement UAT tests
GENERAL LEDGER, REPORTING & COMPLIANCE — NXGN-202 · Wave C · 37 pts (5 stories)
NXGN-728 Finance Controller — Expense Accrual & Prepaid Amortization GL/BIR · W4 8 Period-end accrual logic — complex GL impact; required for UAT scenario testing
NXGN-438 Tax Compliance Officer — Generate BIR Tax Return Summaries GL/BIR · W4 8 BIR compliance reporting — high UAT priority; Tax Compliance Officer role must validate
NXGN-256 Consolidated Financial Reporting & External Audit Compliance GL/BIR · W4 8 External audit package — CFO/Steering Committee sign-off story
NXGN-241 Financial Statement Generation (Standard Reports) GL/BIR · W4 8 P&L, Balance Sheet, Cash Flow — required for Wave C UAT completion
NXGN-431 Trial Balance Report & GL Inquiry GL/BIR · W4 5 Foundational GL query — used by all UAT testers as baseline audit tool
MULTI-ENTITY (PULLED INTO MVP Jun 1) — NXGN-457 · Wave C · 21 pts (3 stories) · supports NXGN-256 · NOT yet groomed
NXGN-484 Finance Admin — Set Up & Manage Legal Entities / Subsidiaries Multi-Entity · W4 5 Entity master — prerequisite for consolidated reporting (NXGN-256)
NXGN-485 Finance Controller — Record & Manage Intercompany Transactions Multi-Entity · W4 8 Intercompany posting — feeds elimination entries in consolidation
NXGN-486 Finance Controller — Run Intercompany Reconciliation & Elimination Entries Multi-Entity · W4 8 Elimination engine — required for NXGN-256 consolidated audit package
UAT Milestone Impact — What S8 Unlocks
Wave B — Core Build Done (S7)
FA Close Required
FA backlog (260/261/263 + 1681, 23 pts) closed in S8 — registry/depreciation/revaluation already Done in S7. The chain hands off for testing once a window is set; full FA + Materials scope complete at S8 close. Testers: AP, Procurement, Materials, FA roles.
Wave C — In Development
Critical-Path Chain
Wave C = 121 pts open, Band 1 = 109. 16 delivered in S8 (Trial Balance + SoD 431/1684, Bank recon 254); the Band-1 set beyond S8 (entity/IC foundation, 256 consolidation, first-close recons, BIR returns, treasury ops) is the S9/S10 spine — window to be re-proposed once S9 is committed. Testers: Finance Controller, Cashier, Tax Compliance roles.
BI — Post-Go-Live Wave
Data Layer Rides S9
Per the banding, only the BI data layer (NXGN-1003, 5 pts — the contract devs build against) is go-live-critical and rides S9. The dashboard suite (72 pts, Band 2) ships post-go-live; exec reporting continues on existing artifacts until then.
Capacity & Delivery Outlook
97
S8 Committed (20 stories)
101
Recent 3-Sprint Avg
707
Remaining (live , banded)
707
Open backlog (live Jun 17 · S9 not yet in Jira)
S8 delivered (97/97 · 20 stories · 100%, 0 carryover): the binding constraint is the UAT gates, not raw capacity. Delivered work — Wave B close (FA 20 + Materials 9 = 29), the COFP cluster + Sales/CRM (1668/1385/1386 + 1215/1216 = 23), Wave C seed (Trial Balance + SoD 431/1684 = 11, Bank recon 254 = 5), cross-cutting enablers (1686/1687/1688 = 16), and the migration start (1689/1690 = 13) — a clean fit at the recent pace, canary (≥90) passing. Live Jun 17: remaining 707 pts and banded — Band-1 go-live-critical (334 across chains; A–D Band-1 = 206) needs well under capacity S9–S12, with a ~47–93 pt A–D Band-2 fast-follow into September; the rest of Band 2 ships Sep–Nov. Epics are six value chains; Jun-17 grooming added 5 P2P/platform stories (+14, Band 2 except notarized-upload 2027). S9 (planned @115): A re-cert + B UAT (open Jun 17), the T2C entity/IC + first-close foundation (Wave C gate + JV's July-load prereqs). Migration is dual-source, 123 pts on the JV lane incl. the in-flight-project loaders.
S8 Committed — Open Items & Carried to S9
Open Items / Carried to S9
Nominate testers for the P2P chain this week — AP, Procurement, Materials, Fixed Assets roles must be identified before Jun 6.
Confirm BI MVP scope — which of the 56 BI dashboard pts are must-have for Sep 1 go-live. Decision needed before S9 planning Jun 16.
Nominate Wave C UAT testers — Finance Controller, Cashier, Tax Compliance Officer roles must prepare test scripts by Jun 20.
S8 Committed — Story Status
FA stories groomed & ready — NXGN-260, 261, 263 are scored, acceptance criteria defined (carry stories from S7).
BI foundation deferred to S9 — NXGN-1003 (5), 1004 (5), 1005 (3), 1671 (3) groomed & scored but did not make the S8 commitment; commit at S9 planning Jun 16.
Wave C seeded in S8 — Trial Balance NXGN-431 + SoD 1684 (11) and Bank recon NXGN-254 (5) committed. Wave C (T2C chain epic NXGN-202) is now 164 pts, of which 122 are Band-1 go-live-critical: entity/IC foundation (484/485/486/488 + 1780/1781), 256 Part A consolidation engine, the first-close set (241/728/1812/1813/recons/input-VAT), 438 BIR, and treasury ops — the S9/S10 critical path.
Capacity confirmed — committed S8 = W3 close (29) + COFP/Sales (23) + W4 seed (16) + enablers (16) + migration start (13) = 97 pts. Recent pace 101 vs ~89-pt floor — comfortable, no carryover.
NXGN ERP Program · S8 closed 97/97 (100%) · S9 active · · Confidential
S6
Sprint 6 — Closed ✓ (May 11)
Apr 27 – May 11, 2026  ·  S7 closed Jun 1 (124/124 · 100%)
91
Committed
91
Done
20
Stories
3
Epics
Sprint Done
121%
vs Baseline
Sprint Progress
91 / 91 pts  ·  Closed May 11 ✓
● All 20 stories Done — sprint complete
✅ S7 Closed (May 16 – Jun 1) — 124/124 delivered (100%) · 28 stories Done · 0 carryover. Wave B epics AP, Procurement & Materials core COMPLETE at S7 close; 34 pts dev backlog (FA 23 + Materials enhancements 11) → S8. (Forward picture since re-baselined Jun 4–6 — see exec brief; chains have since reopened with audited gap scope, so no chain is currently dev-complete.)
Sprint Burndown
May 1 excluded (PH Labor Day). Ideal = 91 pts ÷ 10 working days.
✓ Wave A DEV COMPLETE — handed to UAT
NXGN-119 core & NXGN-204 all Done. 5 enhancement/UAT stories (25 pts) open — schedule S8.
✓ Procurement DEV COMPLETE (NXGN-118)
All 15 stories Done in S6 — 57 pts delivered. Enhancement scope (rescored 36 pts) fully closed in S7 — 10/10 Done. Procurement epic COMPLETE. Wave B remaining: 34 pts (FA 23 + Materials enhancements 11) → S8.
Performance Scorecard
Velocity & Story Complexity Trend

Sprint Velocity — Points Delivered per Sprint

Story Size Distribution — S1 to S7

Sprint-by-Sprint Detail
SprintDatesPts DeliveredIssuesAvg SizeIssue TypesLoad vs BaselineModules Covered
Delivered points per closed sprint (velocity source: closed-sprint Done issues).
Qualitative Assessment
Velocity Growth — New Record (124 pts · 100%)
S1→S7 rose 130% (54 to 124 pts). S7 delivered all 124 committed pts — the highest sprint in project history and the first 100%-commitment sprint, 65% above the 75-pt baseline. 7-sprint stats: mean 78, median 75, max 124 (S7), min 48 (S2); recent 3-sprint avg (S5–S7: 101 pts), with the S7 record (124), brackets the adopted 115-pt planning basis for S9–S12.
Developer Engagement — Convention Step-Change
S7 generated 178 GitHub commits at 91% Jira convention — up from 28% in S6. Arron Manlapaz 134, Vincent Mendoza 20, JV Del Rosario 17 (back online), Arvin Libo 7. All 28 sprint stories have commit evidence (100% coverage) — every story is traceable to code.
Wave B Core Complete — 34 pts Backlog to S8
At S7 close, the Wave A and B module cores were all dev-complete (Collections, AR, Sales/CRM, Procurement, AP, Materials, FA foundation). Since then the Jun 4–6 audits reopened every chain with gap scope, and modules were consolidated into six value-chain epics — current status lives on the UAT tab.
S7 Closed — 100% Commitment, 0 Carryover
S7 closed at 124/124 (100%) — the team's first full-commitment sprint and best result yet. All 28 stories Done; the final 5 (Vendor Advance 592, Supplier Price List 1214, Item Master 1388, Low Stock Alerts 153, Asset Revaluation 262) all landed before close. Nothing carried over. Wave B core was dev-complete at S7 close (since reopened by the Jun 4–6 gap audits).
NXGN ERP Program · wrld capital holdings · Sprint Performance Report · · Confidential
GitHub data: Wrld-Capital-Holdings-Inc/ERP · Jira: wrldcapital.atlassian.net · Velocity source: closed sprint Done issues
S7
Sprint 7  CLOSED ✓
May 16 – Jun 1, 2026  ·  Closed Jun 1 (review Jun 2)  ·  124 pts done (100%) · 0 carryover ✓
124
Committed
28
Stories
4
Epics
124
Done
100%
Delivered
Sprint Timeline
Closed Jun 1  ·  124/124 pts done (100%)
● Sprint closed — full commitment met · 0 carryover
Wave B core dev-complete at S7 close.  AP, Procurement & Materials core epics COMPLETE; Fixed-Asset registry, depreciation & revaluation shipped. 34 pts Wave B dev backlog (FA 260/261/263 + 1681 = 23; Materials 1678/1679/1680 = 11) → S8. BI infra → S8.
AP & Vendor · NXGN-203
Done ✓
6/6 Done (36 pts) ✓ · epic complete
Wave B · core done at S7 ✓
Procurement · NXGN-118
Done ✓
10/10 Done (36 pts) ✓ · epic complete
Wave B · core done at S7 ✓
Materials Inv · NXGN-120
Done ✓
9/9 Done (37 pts) ✓ · epic complete
Wave B · core done at S7 ✓
Fixed Assets · NXGN-205
Closed ✓
6/6 Done ✓ · 258/259/262 (S7) + 260/261/263 + 1681 delivered in S8
Wave B · registry+deprec+reval done · closes S8
Sprint Calendar
Sprint startMay 16, 2026
Sprint endJun 1, 2026
Working days11 days
StatusClosed Jun 1 · review Jun 2
Committed124 pts
Delivered124 pts · 28 stories
Carry to S80 pts (none)
Commitment met100% ✓
Velocity Context
S7 delivered124 pts
S7 committed124 pts
S5–S7 avg101 pts
Commitment met100% ✓
S7 delivered all 124 of 124 (100%) — new record, 0 carryover. The S5–S7 avg (101) and the S7 record (124) bracket the adopted 115-pt planning basis for S9–S12.
S8 Preview (Jun 2 – Jun 16)
W3 dev 34 (FA 23 + Materials 11) + COFP cluster 20 + Bank 21 + clean GL 16 = ~91 pts (no carryover).
Split 241/438 + NXGN-256 decision at planning; BI foundation 16 + Wave-2 follow-ups 25 backfill.
S5
Sprint 5 — Closed Apr 22
Apr 8 – Apr 22, 2026  ·  88 pts confirmed Done  ·  87 pts committed
100% — all 19 Done ✓
S5 Points Delivered
88
Sprint closed Apr 22 — record sprint
New project high — 17% above 75-pt baseline
S5 Final Status
CLOSED
88 pts confirmed Done · all 19 stories
Sprint 6 started Apr 22
Wave A Status
DONE
All 4 NXGN-207 stories closed
18 pts delivered — Wave A complete
Epics Active
7
Across 4 UAT waves
Broadest wave coverage to date
Developer Activity — Sprint 5 (GitHub · Apr 8–20)

Daily Commit Activity by Developer

Arron
JVCoder
Vincent
Arvin (aql)

Commits by Developer — S5 Total

Commit Analysis & Individual Productivity — Sprint 5 (excl. merge commits)
Arron
wrld-arron-dev
8
commits in S5
23.3K
Lines Added
1,623
Lines Removed
194
Files Changed
5
Active Days
13 pts
Total Assigned
2.6
Avg Pts / Story
38% sprint cadence (5 of 13 days)
Features
Audit Trail / Hash ChainDHSUD PDF ReportMaceda Law Validation
Jira Convention25% · 2 of 8 commits ⚠
JVCoder
JVCoder · JVDel-hub (alt)
11
commits in S5
20.6K
Lines Added
3,228
Lines Removed
181
Files Changed
6
Active Days
5 pts
Total Assigned
1.7
Avg Pts / Story
46% sprint cadence (6 of 13 days) — highest on team
Features
Commission SchedulerLogin RedesignEmployee & Agent UsersUAT Bug Capture
Jira Convention9% · 1 of 11 commits ✗
Arvin
wrld-dev-25 · aql-tagged
3
commits in S5
13.5K
Lines Added
1,484
Lines Removed
118
Files Changed
2
Active Days
18 pts
Total Assigned
4.5
Avg Pts / Story
15% sprint cadence (2 of 13 days) — lowest on team
Features
Sales/Procurement ModuleMaterial CodesNXGN-253 Bank Feed
Jira Convention0% · date-stamp style only ✗
Vincent
wrld-dev-25 · non-aql
6
commits in S5
6.5K
Lines Added
2,303
Lines Removed
86
Files Changed
4
Active Days
5 pts
Total Assigned
1.3
Avg Pts / Story
31% sprint cadence (4 of 13 days)
Features
Canvass & Materials (131/133)Credit Memo (588)AR Reconciliation (589)
Jira Convention0% · bare numbers only ✗

Code Output — Lines Added per Developer (non-merge commits)

Sprint Cadence & Commit Convention

DeveloperCommitsActive DaysJira RefsAvg +Lines
Arron85 / 1322,917
JVCoder116 / 1311,869
Arvin32 / 1304,485
Vincent64 / 1301,091
Commit Log — Sprint 5 (Apr 8–20 · excl. merge commits · newest first)
DateDeveloperSHACommit Message+ Lines− LinesFilesJira
wrld-dev-25 is a shared account. Arvin = aql date-stamp commits; Vincent = remaining wrld-dev-25. JVDel-hub is JVCoder's secondary account.
GitHub → Jira Cross-Check — Sprint 5 Stories
TicketSummaryPtsDeveloperJira StatusGitHubCommit Evidence
GitHub evidence matched by commit message keyword, ticket reference, or feature name.
Workflow Observations
main branch is 3 months stale (last merge: Jan 22)
All S5 development is landing in personal branches (Arron, JVCoder, Arvin-V2, Vincent) and merging only to Develop. The main branch has not been updated since January 22, 2026 — 89 days ago. Recommend establishing a weekly Develop → main merge cadence.
Inconsistent commit conventions reduce traceability
Only Arron consistently references NXGN ticket keys. JVCoder uses feature names, Vincent uses bare numbers (588, 131, 133), Arvin uses date stamps. This makes automated tracking unreliable for 75% of the team.
NXGN-257 (Audit Trail) — confirmed Done in S5
Arron had 5+ commits on audit trail immutability and hash chain logic (NXGN-1151–1156, Apr 16–17). Story confirmed Done at S5 close (Apr 22) — included in the 88 pts delivered.
NXGN-253 (Bank Feed Integration) — confirmed Done in S5
Flagged as at-risk mid-sprint due to limited commit evidence. Story confirmed Done at S5 close (Apr 22) along with all 18 other S5 stories.
131
Open / Unscheduled
707
Remaining Pts
72
Showing
445
Showing Pts
0
Sim Pts
0
Sim Stories
Jira pull:
Epics = value chains (Jun 6 reorg) · banded per S9 re-baseline proposal
Wave:
Size:
Group:
Key Summary Wave Pts ↕ + Sprint
Remaining Points by Epic
Points by Wave
Wave Breakdown
⚡ Sprint Simulator
Click [+] on any story to add to sprint plan
Sprint Target
115 pts
0 pts of 115 target
Add stories to begin planning
Developer Scorecards — Sprint-over-Sprint
Each scorecard compares a developer against their own history — there is no cross-developer ranking. Story points measure delivery flow, not value: reviews, pairing, and unpointed work don't appear here. Team goals: deliver what you commit · ≥95% of commits reference an NXGN ticket · every story carries commit evidence.
QA Scorecards — Verification Throughput
QA works on per-story verification subtasks ("QA — …", paired: one per QA per story). Same rules as above — self-trend only, no ranking. Months shown by subtask creation.
Data: Jira completion-sprint attribution + full QA-subtask history (live Jira ). Close-out basis: Jira stores a single sprint per issue here — rates reflect final attribution; mid-sprint moves are not retained by the field · GitHub Develop non-merge commits · S8 delivered 97/97 (100%, 0 carryover); per-sprint commit telemetry is the Jun-10 partial pull — final-branch S8 commit re-pull pending.